CISCO-646-391 v2.83 Demo

1.In the implement phase, solution implementation involves which of the following task?

 

A: analyze high-level design and technology requirements of the customer

B: perform preliminary Site Assessment

C: configure core products

D: execute test cases

Correct Answers:  C

 

2.Which of the following is a key objective of operations readiness assessment in the plan phase?

 

A: assess the ability of site facilities to accommodate the proposed solution

B: assess existing network infrastructure and applications to verify its ability to support the proposed system

C: assess the current state of operations and network management infrastructure, including people, processes, and tools, to identify issues and opportunities

D: install and test system components in a nonproduction environment

Correct Answers:  C

 

3.In the operate phase, the task of analyzing process exceptions belongs to which service component?

 

A: Problem Management

B: Service Assurance

C: Change Management

D: Incident Management

E: Security Administration

Correct Answers:  B

 

4.In the implement phase, the ongoing support hand-off meeting provides which of the following benefits?

 

A: improves customer satisfaction by ensuring a productive operations environment of systems and processes; and minimizes the time it takes to migrate the customer into an automated and process-oriented environment, realizing productivity benefits from operations resources

B: provides the customer with necessary reactive break-fix services required for daily operation of the network, the availability of reactive break-fix services being a requirement for customer acceptance of the implementation

C: establishes both an ongoing review process to ensure that issues are addressed promptly and that the partner can assess and position service activities proactively and a communications mechanism to help the partner maintain awareness of the customer’s issues

D: improves customer satisfaction by ensuring a productive operations environment of systems and processes; and minimizes the time it takes to migrate the customer into an automated and process-oriented environment, realizing productivity benefits from operations resources

Correct Answers:  B

 

5.Network readiness assessment is an important service component in the plan phase. Which task is part of network readiness assessment?

 

A: accounting for all advanced technology system assets and configurations

B: conducting a discovery workshop to gather data and initiate network implementation plan development

C: assessing current infrastructure and applications and their readiness to support proposed advanced technology system

D: documenting network availability and redundancy requirements

E: developing Site Readiness Assessment Report

F: conducting Operations Readiness Assessment

Correct Answers:  C

 

6.Low level design, site readiness report, project management plan, network implementation plan, and systems acceptance test plan are pre-requisites for which service component in the design phase?

 

A: Implementation Kick-off Meeting

B: Staff Plan Development

C: Staging Plan

D: Project Kick-off

E: Migration Plan Development

F: Business Plan

Correct Answers:  E

 

7.Developing a baseline network element configuration for networking and applications devices to be implemented in a network is a deliverable for which service component in the design phase?

 

A: Detailed Design Development

B: Systems Acceptance Test Plan Development

C: Staging Plan

D: Implementation Plan Development

E: Project Kick-off

Correct Answers:  D

 

8.Assessing the existing network infrastructure is a task conducted as part of which service component in the plan phase?

 

A: Operations Readiness Assessment

B: Detailed Design Development

C: Solution Implementation

D: Account Planning

E: Network Readiness Assessment

Correct Answers:  E

 

9.In the implement phase, project planning comprises which of the following tasks?

 

A: confirm project and milestone dates, as well as project and cutover roles and responsibilities

B: install, configure, and provision core products

C: update and document logical and physical topology maps and serial numbers

D: confirm deployment team, craft project plan, create communication and escalation plans

Correct Answers:  D

 

10.Which two tasks are executed in the service assurance service component within the operate phase? (Choose two.)

 

A:analyze process exceptions

B:prepare a service readiness report

C:send internal/external surveys

D:review remediation plan from operational assessment

Correct Answers:  A, C